09/02/09 – Completed sidewalk on the north side of 200 E. Grand from the west end looking east.

Store entrances with steps are being retrofitted with ADA-compliant ramps as necessary. Handrails will be added later to this ramp in the 200 block of E. Grand.
All sidewalk ramps within the project limits will be reconstructed with new ADA-compliant tactile warning mats
The downtown sidewalk improvement project began on Monday, June 29, 2009. This is a project to replace sidewalks along both sides of Grand Avenue from Oak Street to Third Street and on First Street from Grand Avenue north to the alley. The project schedule above shows the approximate dates of when construction will occur in each block within the project limits.
This schedule will be updated as work progresses and construction time estimates are refined. For information regarding this project contact Mike Lane, Traffic Engineering Manager, at (580) 767-0327.